First Endurance 50kW Wind Turbine in Yorkshire is Exceeding Expectation!
After a very exciting few weeks following the install of Earthmill’s first 50kW Endurance wind turbine we were especially delighted when we checked in with the turbines owner, farmer Tom Mellor, to see that the turbine is exceeding expectation.
Following an average week of wind the turbine is doing over 1,200 units daily. This is fantastic news for Tom and of course excellent news for Earthmill.
Tom has very kindly allowed Earthmill to hold two Open Days on Wednesday 29 June 2011 and Thursday 21 July 2011. This is a fantastic opportunity for people interested in the 50kW turbine to come and see it in action.
The team from Earthmill and Endurance Wind Power will be on hand to answer any questions you may have regarding the operation, planning and installation of the turbine. In addition the turbine owner will be around to answer any questions you may have regarding his personal experience of the process.
Places are limited so please contact the office on 01937 581011 or alternatively e-mail info@earthmill.co.uk to book your place.
Finally Steve Milner (Managing Director of Earthmill) will be attending the National Farmers Union walk at the site near Hunmanby on Friday 17 June 2011. If you are due to attend the walk this is also a really good opportunity to put your questions to Steve and see the turbine in person.
News Filter
Date
-
2011
-
2012
-
2013
-
2014
-
2015
-
2016
-
2017
-
2018
-
2019
-
2020
-
2022
News
Installation of the first 50kW Endurance turbine is complete!
The highly anticipated 50kW Endurance turbine has been installed. After the incredible journey the turbine has taken leaving Canada approximately a month ago, the turbine is now standing proud at Wold Top Brewery. There will be an open day for the turbine on the 29th June at Wold Top Brewery. If this is something that you are interested in attending, please do not hesitate to contact us at the office on:
Tel: 01937 581011
or e-mail at: info@earthmill.co.uk
For any individuals who are considering the 50kW Endurance turbine this is a really good opportunity to see it in all its glory and get all the answers to your burning questions.
Be sure to check out Wold Top Brewery: http://www.woldtopbrewery.co.uk/
News Filter
Date
-
2011
-
2012
-
2013
-
2014
-
2015
-
2016
-
2017
-
2018
-
2019
-
2020
-
2022
News
Installation has begun of 2 Endurance turbines at Wold Top Brewery
On Thursday 26th May installation began on 2 brand new Endurance turbines at Wold Top Brewery. This is Yorkshire’s first Endurance turbines to be installed! Armed with a crane a telescopic handler and man power the team began work with offloading the tower. This was constructed on the floor bolting the two parts together and attaching the fall arrest system. Once that was complete it was attached to the crane and hoisted up where it was then placed into the foundations. Steve then climbed the tower to unhook the crane and the first part was complete. Dave Broadbank our new Operations Manager said “It was easier then we first anticipated and we have learnt lessons that will help us with the installation for the ones to follow”
News Filter
Date
-
2011
-
2012
-
2013
-
2014
-
2015
-
2016
-
2017
-
2018
-
2019
-
2020
-
2022
News
Yorkshire’s first Endurance Wind Turbine
Earthmill are entering into a very exciting week with the installation beginning of Yorkshire’s first Endurance Turbine. This is something that Endurance and Earthmill have worked very hard to achieve. We will be taking you through the stages step by step as they happen. The culmination of this will be an open day for the launch of the turbine. Stay tuned to find out how it goes.